5 tracked AI data center projects in Reeves County, Texas, 8.1 GW of disclosed planned capacity across 5 of them. Status: 1 under construction, 4 pre-construction.

5Tracked projects
8.1 GWDisclosed capacity
8Operators
3.07MW per sq mi2,635.4 sq mi of land

Status

  • 1 Under construction
  • 4 Pre-construction

Power strategy

  • 3 Behind-the-meter gas
  • 2 Hybrid (grid + on-site)

Projects

  • Microsoft Pecos Data Center (Reeves County) Pre-construction · 2.0 GW · Pecos

    Once a speculative line in Cleanview's data, now one of Microsoft's largest single builds: a ~2 GW Permian Basin campus powered behind-the-meter by Chevron's co-located 2.67 GW 'Project Kilby' gas plant under a 20-year deal, a flagship of the off-grid, power-first model Texas builders are racing toward.

  • Alpha Digital Campus Pre-construction · 2.0 GW · Northern Reeves County (Waha Hub area)

    LandBridge's flagship 'powered land' play: Five Point-backed PowerBridge holds an option on ~3,400 acres near the Waha Hub for a pad-ready, private-use-network campus of up to 2 GW on co-located combined-cycle gas, advancing incrementally, starting with a 58.3 MW ERCOT filing.

  • Core Scientific Pecos Campus (Cottonwood 1 & 2) Under construction · 1.5 GW · Pecos

    Core Scientific's second Texas bitcoin-to-AI conversion after Denton, and its biggest: the 300 MW Cottonwood mining campus outside the city of Pecos (Reeves County) is being rebuilt toward 1.5 GW gross / 1.0 GW leasable high-density AI colocation on a hybrid grid-plus-BTM power design, with the first data hall up in 2026 and initial capacity due early 2027.

  • Prometheus Hyperscale Pecos Campus Pre-construction · 1.5 GW · Pecos

    A proposed hyperscale campus in Reeves County near Pecos, planned by Prometheus Hyperscale with Istmo Energy for 1.5 GW of Phase 1 IT capacity and a path to about 2.5 GW. The design runs the first phase behind its own generation rather than through the ERCOT queue. No binding tenant has been announced and no construction has started.

  • NRG Delaware Basin Hyperscale Project Pre-construction · 1.1 GW · Delaware Basin (Waha Hub area)

    A power-anchor project in the classic powered-land mold: NRG and LandBridge's September 2025 agreement frames a 1.1 GW grid-connected gas plant on LandBridge acreage near the Waha Hub, purpose-built to land a hyperscale data center, but construction waits on a signed PPA, making this the most conditional of Reeves County's giga-scale plans.