No. 15 · September 18, 2026

ERCOT targets 25MW+

ERCOT asked every data center of 25 MW or more seeking interconnection for impact data by October 12, the governor ordered penalties for data centers that skipped the state water survey, and the attorney general opened an investigation into the Blueprint site in Taylor.

The lead

The state spent the week asking data centers to account for themselves. ERCOT posted a request for information on September 14 addressed to every data center of 25 MW or more pursuing interconnection, covering tax benefits, on-site generation, water, noise and ownership, with submissions due October 12. The same day Governor Greg Abbott directed the Texas Water Development Board to enforce the water-use survey against data centers that did not file, with a progress report due to his office by October 14. On September 17 Attorney General Ken Paxton said his office is investigating whether the Blueprint site in Taylor is bound by a 1999 parkland trust.

What the answers will be used for is less clear. ERCOT's page does not say whether a response is mandatory or what happens to a developer that does not file, and some coverage describing the deadline as a condition of interconnection goes further than the page does. The governor's directive names no facility. Paxton's investigation has made no finding. Fort Worth is drafting a 250 foot residential setback and required noise studies, and none of it is adopted.

The filings did not wait. Digital Realty filed for an 80 MW, $300 million building on its Garland campus, DataBank for a $425 million building at Red Oak, and two registrations at Cedar Creek add $1.2 billion, all state-form estimates with target dates. Crusoe raised $3.9 billion and named Abilene as the platform it will scale. Oracle said it has backed more than 1.7 GW of Texas wind, and ENGIE agreed to supply up to 568 MW for Oracle's Texas operations.

17Items this week
17Promoted to Intel
70 GWBiggest number
The rundown

ERCOT wants to know who owns the load, and it has not said what happens to a developer that stays silent.

Three companies are paying for Colorado City's water, and Cipher says its site takes none of it.

Digital Realty's Garland filing is the only one of the week's three large permits to carry a megawatt figure.

Meta's seventh Apex contract lands in Gonzales County with no data center attached.

The wire
Projects & Milestones5
Power & Grid4
Environment & Real Estate1
Finance & Corporate2
Government & Community5

You’re reading The Load Zone, the weekly Texas AI data center news wire from the Texas AI Data Center Intelligence Hub. Items that meet the intelligence bar are promoted into the Intelligence →.