LandBridge × NRG 1.1 GW power-anchor site
Pre-construction

A power-anchor project in the classic powered-land mold: NRG and LandBridge's September 2025 agreement frames a 1.1 GW grid-connected gas plant on LandBridge acreage near the Waha Hub, purpose-built to land a hyperscale data center, but construction waits on a signed PPA, making this the most conditional of Reeves County's giga-scale plans.

1.1 GWPlanned power
Developer
NRG Energy, Inc. (power) with LandBridge Company LLC (land)
Owner
NRG Energy (generation); LandBridge (surface)
Tenant
Hyperscale data center operator: to be determined
Power detail
1,100 MW grid-connected gas plant designed to anchor a future hyperscale data center; data center capacity itself not separately disclosed
Power source
Grid-connected 1.1 GW natural gas plant near the Waha Hub, with grid export capability during statewide strain
Cooling
Not disclosed
Compute
TBD
Construction start
TBD: contingent on FID (long-term PPA with a creditworthy data center operator)
Est. completion
In-service as early as year-end 2029
Grid strategy
Hybrid (grid + on-site)
County
Reeves
Nearest city
Delaware Basin (Waha Hub area)
Announced
2025-09-23