Dallas County

Last updated

6 tracked AI data center projects in Dallas County, Texas, 534 MW of disclosed planned capacity across 4 of them. Status: 4 under construction, 2 pre-construction.

6Tracked projects
534 MWDisclosed capacity
7Operators
0.61MW per sq mi873.2 sq mi of land

Status

  • 4 Under construction
  • 2 Pre-construction

Power strategy

  • 5 ERCOT grid
  • 1 TBD

Projects

  • Stream Wilmer II Hyperscale Campus (DFW C) Under construction · 240 MW · Wilmer

    Stream's SECOND Wilmer campus, distinct from the tracked DFW VIII site: 140 acres at 930 N Sunrise Road against DFW VIII's 77 acres at 300 S Sunrise Road, 240 MW against 90 MW, and a separate legal owner (SDC DFWC, LP vs SDC DFW VIII, L.P.). Surfaced while sweeping DFW VIII and initially easy to mistake for it. Not opened as a tracked project here, this is a lead for a person to decide on.

  • NTT Dallas (Garland) Campus Expansion Under construction · 124 MW · Garland

    NTT's Garland campus keeps absorbing hyperscale demand, part of 130 MW in new contracts across four US campuses and a $10B global buildout through 2027.

  • Stream DFW VIII (Wilmer) Under construction · 90 MW · Wilmer

    Stream's eighth DFW project pushes into Wilmer on the southern I-45 corridor, thin public detail, but another marker of how far the Metroplex buildout now sprawls.

  • Digital Realty DFW45 (Garland) Pre-construction · 80 MW · Garland

    A planned 672,000 sq ft, 80 MW data center at 1602 Ferris Road in Garland, Dallas County, to rise on Digital Realty's Digital Garland Campus as DFW45. A state construction filing (TABS2027000488), reported on September 15, 2026, puts the cost at $300 million, with construction to begin in November 2026 and finish in January 2029. The building includes a loading area and tenant office space. No tenant has been named.

  • QTS DFW1 Campus (DC3) Under construction · — · Irving

    Blackstone-owned QTS adding its third building at the Irving campus, part of the steady DFW colo expansion running underneath the headline gigawatt projects.

  • Equinix DA12 Dallas Pre-construction · — · Dallas

    Equinix's next Dallas interconnection hub: a $540M+, four-story IBX adding 372k sq ft to the most network-dense market in the South.