Stream DFW VIII (Wilmer)

Last updated

South Dallas County build
Under construction

Stream's eighth DFW project pushes into Wilmer on the southern I-45 corridor, thin public detail, but another marker of how far the Metroplex buildout now sprawls.

90 MWPlanned power
Developer
Stream Data Centers
Owner
Stream Data Centers
Tenant
Hyperscale build-to-suit / colo
Power detail
90 MW critical capacity at full build across three hyperscale buildings, served by a dedicated on-site 150 MW Oncor substation pre-designed for full campus capacity, disclosed on Stream's own campus page (DFWB), retrieved 2026-08-11. Previously carried as undisclosed.
Power source
Oncor / ERCOT
Cooling
Not disclosed
Compute
Colocation
Construction start
2025
Est. completion
TBD
Grid strategy
ERCOT grid
County
Dallas
Nearest city
Wilmer
Announced
2023-11-29