Stream Wilmer II Hyperscale Campus (DFW C)

Last updated

DFWC / DFWC1, 930 N Sunrise Road
Under construction

Stream's SECOND Wilmer campus, distinct from the tracked DFW VIII site: 140 acres at 930 N Sunrise Road against DFW VIII's 77 acres at 300 S Sunrise Road, 240 MW against 90 MW, and a separate legal owner (SDC DFWC, LP vs SDC DFW VIII, L.P.). Surfaced while sweeping DFW VIII and initially easy to mistake for it. Not opened as a tracked project here, this is a lead for a person to decide on.

240 MWPlanned power
Developer
Stream Data Centers
Owner
SDC DFWC, LP
Power detail
240 MW planned critical capacity across the campus, served by a 372 MW on-site dedicated Oncor substation, per Stream's own campus page. First building DFWC1 is a two-story, 360,750 sq ft data center at 48 MW.
Construction start
2026-04-01 (DFWC1, per TDLR filing)
Est. completion
DFWC1 completion 2027-10-27 per TDLR filing; full campus phased, undisclosed
Grid strategy
ERCOT grid
County
Dallas
Nearest city
Wilmer