← All Projects

Sangha Project Genesis (Ector County)

Last updated

Project Genesis
Pre-construction

A 110.4 MW Sangha Renewables data center campus in Ector County, announced as Project Genesis and developed alongside utility scale solar. ERCOT conditionally classified it as Base Load under Batch Zero on September 11, 2026. About 19.9 MW is available now, with a further 90.5 MW expected in May 2028. Marathon Capital is running a strategic process for the project.

110.4 MWPlanned power
Developer
Sangha Renewables
Owner
Sangha Renewables
Tenant
Not disclosed
Power detail
110.4 MW conditionally classified as Base Load by ERCOT under Batch Zero on September 11, 2026. About 19.9 MW is currently available; Sangha says rights to a further 90.5 MW are expected in May 2028. The classification is conditional on ERCOT's audit and verification.
Power source
ERCOT grid, with utility scale solar developed alongside the campus
Cooling
Not disclosed
Compute
Marketed to AI, cloud, inference and high performance computing workloads, per the company
Grid strategy
ERCOT grid
County
Ector