Nexus Data Centers Hubbard

Last updated

Hill County behind-the-meter campus
Under construction

A quiet giant that stopped being quiet: a behind-the-meter campus outside tiny Hubbard, now with a $400M, 491,378 sq ft first building on a state construction filing, two nine-figure credit facilities and a private-equity backer, while the gas plant meant to power it is still waiting on its TCEQ air permit and the 7.2 GW headline remains unreconciled with the 600 to 612 MW the trade press describes.

7.2 GWPlanned power
Developer
Nexus Data Centers
Owner
Nexus Data Centers (site entity: Nexus Data Centers Hubbard LLC, The Woodlands, TX; holdco: Nexus Apex Holdings, LLC)
Tenant
Anthropic (reported primary tenant, not company-confirmed)
Power detail
UNRESOLVED CAPACITY GAP: do not treat these as one number. The 7,200 MW carried here is the full-buildout figure from Cleanview's April 2026 analysis (the basis for calling this the state's 2nd-largest planned project). Trade coverage of the announced campus instead consistently describes 600 to 612 MW of behind-the-meter gas (DCD, Data Center View, Data Center Map). Search-result summaries of a developer-or-opposition site that does not resolve claim the TCEQ application covers ~7,230 MW of continuous generation plus ~19.5 MW of emergency standby, which would reconcile the two as permitted generation vs near-term data center load. That claim could NOT be verified and is not ingested. The gap stands open pending a direct read of the TCEQ application. A THIRD figure entered reporting Jul 30, 2026: Reuters, citing the WSJ, described a ~1.6 GW natural-gas plant tied to a reported (unclosed) ~$15B financing for the campus, held alongside, not reconciled with, the other two.
Power source
Behind-the-meter on-site natural gas turbines with backup diesel generators: TCEQ air authorization applied for and still under review as of this writing, so the power island is not yet permitted
Cooling
AirJoule metal-organic-framework units to produce high-purity distilled water from data hall waste heat under an on-site Water Purchase Agreement; first systems targeted 2H 2026 (announced Dec 2, 2025; commercial terms undisclosed)
Compute
TBD
Construction start
Jan 6, 2026 (start date recorded on the TDLR project registration)
Est. completion
First building Oct 29, 2027 (TDLR filing); AirJoule water systems targeted 2H 2026
Grid strategy
Behind-the-meter gas
County
Hill
Nearest city
Hubbard (between Waco and Corsicana)
Announced
2026-04-13