← All Counties

Hill County

Last updated

2 tracked AI data center projects in Hill County, Texas, 7.6 GW of disclosed planned capacity across 2 of them. Status: 2 under construction.

2Tracked projects
7.6 GWDisclosed capacity
6Operators
7.93MW per sq mi958.9 sq mi of land

Status

  • 2 Under construction

Power strategy

  • 1 Behind-the-meter gas
  • 1 Hybrid (grid + on-site)

Projects

  • Nexus Data Centers Hubbard Under construction · 7.2 GW · Hubbard (between Waco and Corsicana)

    A quiet giant that stopped being quiet: a behind-the-meter campus outside tiny Hubbard, now with a $400M, 491,378 sq ft first building on a state construction filing, two nine-figure credit facilities and a private-equity backer, while the gas plant meant to power it is still waiting on its TCEQ air permit and the 7.2 GW headline remains unreconciled with the 600 to 612 MW the trade press describes.

  • CyrusOne Bosque–Whitney AI Campus Under construction · 400 MW · Whitney (south of DFW, near Lake Whitney)

    CyrusOne's quiet rural pivot: a hyperscale AI cluster around Whitney and Bosque County, nearly $1B in disclosed building permits, a Calpine 400 MW power deal, and the first tower already topped out.