Core Scientific Hunt County

Last updated

Under construction

Core Scientific's third Texas site and the one it documents in the most detail: 431 MW of planned demand in Hunt County, with interconnection studies complete, the stability study approved, collateral posted, long lead equipment ordered and construction started.

431 MWPlanned power
Developer
Core Scientific, Inc. (NASDAQ: CORZ)
Owner
Core Scientific, Inc.
Power detail
431 MW of planned demand, conditionally classified by ERCOT as Base Load under the Advancing Large Load pathway; the 431 MW stability study is approved. None of it is energised.
Grid strategy
ERCOT grid
County
Hunt
Announced
2026-09-10