Core Scientific Denton (CoreWeave)

Last updated

“One of the largest GPU supercomputers in North America”
Partially operational

The earliest and most mature Texas conversion: Core Scientific's Denton bitcoin site has been rebuilding into a ~260 MW CoreWeave GPU campus since 2024, with the final contracted tranche landing in 2026.

391 MWPlanned power~391 MW gross per Cleanview; ~260 MW critical IT load contracted to CoreWeave after the Feb 2025 +70 MW expansion
Developer
Core Scientific (NASDAQ: CORZ)
Owner
Core Scientific
Tenant
CoreWeave: 12-year hosting contracts; ~590 MW critical IT contracted across six Core Scientific sites
Power source
ERCOT grid (1.3 GW contracted company-wide; ~400 MW still allocated to bitcoin mining)
Cooling
High-density liquid-cooled halls for Nvidia GPUs
Compute
CoreWeave Nvidia GPU clusters
Construction start
H2 2024 (HPC site modifications)
Est. completion
Full campus completion targeted midyear 2026 (Core Scientific guidance, Q4 2025 call, Mar 2, 2026); no completion announcement found as of Aug 12, 2026
Grid strategy
ERCOT grid
County
Denton
Nearest city
Denton (DFW)
Announced
2025-02-26