Bitdeer Rockdale

Last updated

Early works / site prep

About 200 acres Bitdeer bought outright near its existing Rockdale operation in Milam County for roughly $100 million in cash, closed and announced on September 1, 2026, for developing AI and HPC infrastructure. Bitdeer puts its Milam County sites at about 563 MW of interconnected grid capacity, rising to 742 MW under existing plans, with a dedicated water supply and existing transmission and substation infrastructure. No AI or HPC tenant, building design, cooling package or construction filing has been disclosed for the new parcel.

Planned power
Developer
Bitdeer Technologies Group
Power detail
Bitdeer states about 563 MW of interconnected grid capacity across its Milam County sites, and says existing plans take that to 742 MW. The 742 MW covers existing plus pipeline capacity across the sites, not energized load, and neither figure is broken out for the new parcel.
Grid strategy
ERCOT grid
County
Milam
Nearest city
Rockdale