Childress County

Last updated

2 tracked AI data center projects in Childress County, Texas, 1.8 GW of disclosed planned capacity across 2 of them. Status: 1 partially operational, 1 pre-construction.

2Tracked projects
1.8 GWDisclosed capacity
4Operators
2.51MW per sq mi696.5 sq mi of land

Status

  • 1 Partially operational
  • 1 Pre-construction

Power strategy

  • 2 ERCOT grid

Projects

  • Crusoe–Lancium Childress Campus Pre-construction · 1.0 GW · Childress (Texas Panhandle)

    Announced Jul 15, 2026: a 1.0 GW grid-connected AI campus on 270 Lancium-owned acres in Childress County, for an unnamed hyperscaler. It is the second site on the Crusoe-Lancium structure used at Stargate Abilene, Lancium owns the land and the interconnect, Crusoe designs, builds and operates. Distinct from the tracked iren-childress-horizon conversion, which is a different operator and site in the same county. Found while sweeping google-armstrong; the only source retrieved is Crusoe's own announcement, hence 'reported' rather than 'confirmed'.

  • IREN Childress “Horizon” Conversion Partially operational · 750 MW · Childress (Texas Panhandle)

    Texas's biggest operating bitcoin mine is converting in place: IREN's 750 MW Childress campus is adding 200 kW/rack liquid-cooled AI halls while Microsoft GPU workloads move in.