Texas AI Data Center Intelligence Hub

Tracking AI data center development activity across Texas.

Loading dataset…
Planned campus power, stacked — click a segment for the full record
0 MW Widths proportional to planned MW · projects without disclosed power not shown

Map

Marker size scales with planned power. Switch the color mode to see development phase or grid strategy.

Color by:

Grid Strategy

How 60+ GW of planned load is routing around ERCOT's 439 GW interconnection queue.

Disclosed power by grid strategy (GW)

Interconnection status (projects)

Capacity Timeline

AI-relevant capacity additions by quarter from per-project ramp stages. Solid bars = dated phases; faded = estimates.

MW coming online by quarter — dated vs. estimated

AI-relevant capacity only · hover a quarter to see which projects land in it

Key Stats

Disclosed figures only. Click a bar to open the full record.

Planned campus power (MW, log scale)

Disclosed investment / contracted value ($B)

Projects by development phase

Watchlist

Projects carrying live risk flags — opposition, litigation, lost tenants, pauses, or unconfirmed records.

Intelligence Feed

Curated, sourced intelligence events. Raw headlines live on The Load Zone →

Intel activity by month

The Load Zone

The weekly Texas AI data center news wire — twice-weekly sweeps, one edition per week. Items that meet the intelligence bar are promoted into the Intel Feed →

Data Table

Headline fields, sortable. Click a column header to sort, a row to open the full record — or export CSV for every field.

Project Index

Open a card for the full record — specs, companies, risk flags, sources, and intelligence timeline.

Relationship Network

Who leases, backstops, finances, and powers whom. Node size = GW exposure through tracked deals. Click a node.

Reports

Long-form research ingested into the hub, mined for intelligence, archived here with live cross-links.

Companies

Every company with a curated role on a tracked project — who develops, owns, occupies, powers and finances Texas AI data centers.

Portfolio
Counterparties

Projects

Intelligence

Tags

Browse projects and reports by topic tag.

Pricing

The dashboard is free. A subscription buys the history — the complete intelligence archive, and the tools built on it.

Free

$0

Everything current, with an account.

  • The full dashboard — map, charts, KPIs
  • Every tracked project and its current record
  • The company relationship graph
  • The data table, sortable and searchable
  • The Load Zone news wire, all editions
  • Flagship reports in full — always, no account needed
  • The two most recent reports in full, and the opening sections of the rest
  • The most recent intelligence events
  • The weekly digest email, once your address is confirmed
Create a free account

Pro

$299/year

Or $30/month. Everything in Free, plus the archive.

  • The complete event archive — every sourced development, back to 2021
  • Full project records — cost, land, ramp schedule, interconnection detail, confidence and risk flags
  • The full report archive — every county deep-dive in full, not the opening sections

On the roadmap, included when they land

  • Watchlists and email alerts on the projects and counties you follow
  • Exports — CSV and JSON, plus a personal API key
  • The advanced map — pipelines, transmission, generation and service territory on one canvas

Account

Your profile, security, and notification settings.

About

What this hub tracks, where the data comes from, and how it's built.

A living intelligence tracker for AI data center development across Texas.

The hub compiles AI-relevant data center projects from public reporting — frontier campuses, hyperscaler builds, metro colocation expansions, powered-land programs, and bitcoin-to-AI conversions. Every project carries disclosed-vs-estimated power, cost, and land figures, a per-record confidence level, live risk flags, and a sourced intelligence timeline.

Methodology

Each update run logs new developments as dated events first, then updates project state and refreshes review stamps. A strict validation gate (schema + cross-record integrity) runs before any data reaches the database, so figures stay internally consistent and every claim keeps its sources.

How it's built

Astro on Cloudflare Workers with a D1 (SQLite) edge database via Drizzle, a Zod validation gate, and a vanilla-JS single-page front end. Charts use Chart.js, the site map uses Leaflet, and the relationship graph uses D3.

Member access

Log in

Sign in to save watchlists, set alerts, and export briefings.

No account? ·

Account recovery

Reset

We'll email you a link to choose a new password.

Remembered it?

Account recovery

New password

Choose a new password for your account.

At least 10 characters, using three of: lowercase, uppercase, number, symbol.

Create account

Sign up

Get a free account to follow projects and receive intel digests.

At least 10 characters, using three of: lowercase, uppercase, number, symbol.

Already have an account?

← All Reports
Digital Infrastructure Expansion in Tom Green County
Technical, environmental, and socio-political analysis — San Angelo and surrounds

Tom Green County has become a contested frontier for AI infrastructure: a 1.2 GW Skybox/Emergent campus on city land next to an underused AEP substation, a gigawatt-scale Dove Creek proposal that triggered furious rural opposition, the county's only operating colo (Cloudnium SANG-1), and an unannounced Bitdeer build visible only in job postings — all colliding with a recall campaign, a new zoning code, and moratorium talk.

Master inventory

ParameterSkybox/EmergentDove Creek (Beacon)Cloudnium SANG-1Bitdeer
Size1.2 GW target; Ph1 100–250 MWGigawatt-scale (pipeline 3.8 GW / 2 GW registered)6.0→7.8 MWUndisclosed multi-MW
GridAEP Texas / ERCOTAEP Texas / ERCOTAEP TexasGrid-connected
Land~343–350 city acresPrecinct 4, acreage undisclosed10 acresUndisclosed
Floor space6→8 bldgs × 248k sq ft (1.5M→4.5M)Standardized AI shells~286,610 sq ft; 26–30k raised floorModular prefab
Cost$17.4–17.5M land; multi-$B buildout$358.5M wish list$28M acquisition (2019)Undisclosed
StatusZoning approved May 2026; due diligenceEarly exploration; oppositionOperational late 2024Recruiting mid-2026

Skybox/Emergent San Angelo Campus

The largest project ever proposed in the county sits northeast of San Angelo at US-67 and City Farm Road on ~343–350 acres of city-owned 'City Farm' land. In May 2025 the City Council voted 6-0 to negotiate the sale — ~$17.4–17.5M at $50,000/acre. Initial disclosures showed six four-story buildings (~1.5M sq ft); Emergent brochures later expanded the master plan to eight buildings, 1.2 GW, ~4.5M sq ft.

The speed-to-power thesis is the adjacent AEP Red Creek Substation, operating at roughly 10% of its limits. The project sits in due diligence pending legally mandated AEP/ERCOT transmission and load studies on the 1.2 GW draw; construction would phase over ~10 years at 18–24 months per building.

SpecificationValue
Phase 1 target100–250 MW critical IT
CoolingDry, air-cooled closed-loop glycol/water
Permanent jobs120–200 (blended $75–110k)
Staffing mix15% mgmt, 50% critical facilities, 25% security, 10% IT
Municipal revenue~$27M/yr franchise fees

Preview

You are reading 2 of 7 sections of this report.

Read the full report