Texas AI Data Center Intelligence Hub
Map
Marker size scales with planned power. Switch the color mode to see development phase or grid strategy.
Grid Strategy
How tracked projects are securing power, and where they stand in ERCOT's interconnection queue.
Disclosed power by grid strategy (GW)
Interconnection status (projects)
Capacity Timeline
AI-relevant capacity additions by quarter from per-project ramp stages. Solid bars = dated phases; faded = estimates.
MW coming online by quarter — dated vs. estimated
AI-relevant capacity only · hover a quarter to see which projects land in it
Key Stats
Disclosed figures only. Click a bar to open the full record.
Planned campus power (MW, log scale)
Disclosed investment / contracted value ($B)
Projects by development phase
Watchlist
Projects carrying live risk flags — opposition, litigation, lost tenants, pauses, or unconfirmed records.
Intelligence
Weekly Intelligence in your inbox, subscribe to The Load Zone
Intel activity by month
The Load Zone
The weekly Texas AI data center news wire.
The Load Zone — Archive
Every edition of the weekly wire, newest first.
Data Table
Texas AI Data Center Projects
Relationship Network
Reports
Companies
Projects
Intelligence
Coverage
Texas AI Datacenter Map
Calendar
What's ahead for tracked projects: construction starts, completions and deal closes, dated and sourced.
Texas Data Centers by County
Tags
Browse projects and reports by topic tag.
Search
Pricing
Every AI data center project in Texas, sourced, dated, and kept current.
Priced for one person with a corporate card.
Free
$0
Everything current, with an account.
- The full dashboard — map, charts, KPIs
- Every tracked project and its current record
- The company relationship graph
- The data table, sortable and searchable
- The Load Zone news wire, all editions
- Every free report, in full
- The most recent intelligence events
Pro
$399 $399/year
Or $39/month. Everything in Free, plus the archive.
- The complete event archive — every sourced development, not the recent window
- Full project records — cost, land, ramp schedule, interconnection detail, confidence and risk flags
- The full report archive, including any marked Pro-only
- Watchlists — follow the projects and counties you care about
- Advanced Map — every tracked site with coordinates, sized by disclosed capacity and coloured by build status
On the roadmap, included when they land
- Email alerts when a project on your watchlist moves
- Isn't this all public information?
- Yes, and that is the point. Every figure here comes from a filing, a company release, a county record or published reporting, and every record shows its sources. What you are paying for is the work of finding it, dating it, structuring it and keeping it current — across hundreds of projects, every week.
- How current is it?
- The dataset version and run date are in the footer of every page, so you can always tell what you are looking at. New developments are logged as dated events rather than silently edited into records.
- What happens when sources disagree?
- We keep both and say so. Records carry a confidence level, disclosed figures are distinguished from estimated ones, and a blank field means nobody published the number — not that it is zero.
- Can I cancel?
- Any time, from your account. You keep access through the period you have paid for.
Account
Your profile, security, and notification settings.
Profile
- Display name
- Status
- Plan
- Member since
Changing your email address is not available yet — it needs a confirmation round-trip to the new address before the change can be trusted.
About you
- Company
- Your role
- What best describes your work
- Company size
- Industry
- What are you tracking?
Security
Other devices
Signs out every session except this one. Use it if you have signed in somewhere you no longer control.
Preferences
Email Subscriptions
Watchlist
Nothing watched yet.
Digest
Exports
API key
Send it as Authorization: Bearer <key> to the export API. It reads the same data your account can, and cannot change anything.
Billing
Nothing to bill.
Contact
Corrections, questions and data requests, including from the companies we cover.
About
TX AI Intel Hub tracks the companies, projects, power demand, investment, and development activity behind Texas' rapidly expanding AI data center market.
The platform brings together sourced project data, dated intelligence events, company relationships, development status, power requirements, investment figures, and risk indicators in one place.
Coverage focuses on projects that are meaningful to the AI infrastructure buildout: hyperscale campuses, major colocation expansions, powered-land developments, and bitcoin-to-AI conversions.
Every material development is logged as a dated intelligence event and tied back to the relevant project, company, and location.
Project records are updated as new information becomes available, and disclosed figures stay distinct from estimates. Confidence levels and risk flags mark the places where the underlying information is incomplete, conflicting, or still developing.
All records go through automated validation before publication, which keeps projects, companies, locations, and timelines consistent with one another.
Many data center intelligence platforms spread their coverage across projects nationwide. TX AI Intel Hub takes a different approach: stay focused on Texas and go deeper.
That means following projects over time, connecting new developments to existing records, tracking changes in power, investment, ownership, construction status, and risk, and building a historical intelligence trail around each project instead of treating every announcement as a standalone data point.
The result is a more complete view of the Texas AI infrastructure market: not just where projects are, but how they are developing, who is involved, and what is changing.
Pro is built for people who need more than a quick project lookup.
The value is in having the surrounding intelligence ready to hand: deeper project context, connected company and location data, development history, research, and the signals that explain where a project stands and where it may be headed.
Instead of piecing together dozens of articles, filings, announcements, and local reports, Pro gives you a structured intelligence layer for following the Texas AI data center market as it develops.
Log in
Sign in to your account.
No account? · ·
Reset
We'll email you a link to choose a new password.
Remembered it?
New password
Choose a new password for your account.
Sign up
Verification unlocks the network graph, the data table, the full report archive and the weekly newsletter.
Already have an account?
Checking your confirmation…
You're confirmed
A couple of things, then you're in.
Already set a password?
You're in
Your free account is ready.
Free
$0
What your account already includes.
- The full dashboard — map, charts, KPIs
- Every tracked project and its current record
- The company relationship graph
- The Load Zone news wire, all editions
Pro
$399 $399/year
Everything in Free, plus the archive.
One month on from the June deep-dive, Pecos County's megaprojects cleared their two biggest local gates: TCEQ's final air permit for GW Ranch (June 19, the largest power-generation air permit in US history) and Poolside's rezoning filing with Fort Stockton (June 22, hearing July 13). TNMP's $114.8M transmission upgrade heads for August in-service, while Governor Abbott's July 1 rural-ban rhetoric puts the county's off-grid buildout under state-level pressure. The refreshed directory adds Blockstream's 140 MW mine to the county's bitcoin periphery.
What changed since June 10
- GW Ranch: TCEQ approved the final air-quality permit on June 19, 2026 — clearing full-scale construction on the 7.65 GW campus and drawing renewed emissions criticism (33M tons GHG/yr permitted ceiling).
- Project Horizon: Poolside Infrastructure Company, LLC filed a rezoning request with the City of Fort Stockton on June 22; the Board of Adjustment / City Council public hearing is set for July 13, 2026 — a live watch item on ingest day.
- Tarbush / grid: TNMP's $114.8M Pecos County Transmission Improvement Project (Woodhouse 138-kV substation cut into the Tarbush–Leon Creek line) is on track for its August 2026 in-service date.
- Macro politics: Governor Abbott's July 1 call to ban AI data centers in rural residential areas and repeal sales-tax exemptions puts the county's megaprojects under heightened scrutiny (already logged on this tracker's event feed — linked, not re-logged).
GW Ranch: the final permit
The June 19 approval is described as the largest power-generation air permit ever granted in US history, moving GW Ranch from development into active execution: 7.65 GW of gas generation integrated with 1.8 GW of BESS and 750 MW of solar, a dedicated 15-mile 1 BCF/d Waha pipeline, 8,000+ build-ready acres, site prep from Q1 2026, first 1 GW phase in H1 2027, and scaling to 5+ GW by 2031. The project is 'partner-ready' with no disclosed tenants. Environmental groups cite the permitted ceiling of up to 33M tons of greenhouse gases per year (Texas Tribune, Jul 9). This report's June 19 'final' approval sits atop earlier permit dates in this tracker's log — see the June report's permit-date note.
Poolside rezoning watch
The update repeats the June directory's Project Horizon profile — 2 GW, 559 acres, 576 MW BTM gas under construction, $5.5B county abatement, CoreWeave anchor with 40,000+ GB300s — and adds the June 22 rezoning filing, with the public hearing on July 13, 2026 (ingest day; outcome unknown). Reconciliation held open: like the June report, this update makes no mention of CoreWeave's reported April 2026 exit and does not explicitly resolve it; the tracker therefore keeps Project Horizon at-risk while logging the rezoning as evidence the campus is still being actively advanced. Source-integrity flag: the update's citation for the Horizon specs points to an article about the Microsoft/Chevron 'Project Kilby' build in Reeves County — the figures used here are those corroborated by the June report and the projecthorizon-tx.com portal.
Directory refresh — grid-tied incumbents
| Site | Operator | MW | Posture | Since June 10 |
|---|---|---|---|---|
| Fort Stockton Clean Campus | Lancium (a Blackstone company) | 325 (25 active) | Grid / CLR via TNMP | Held up as the county's grid-interactive computing model alongside Jupiter Power's St. Gall BESS assets |
| Cormint Fort Stockton | Cormint Data Systems | 130 | Grid / company substation, 814 acres | Sub-2.3¢/kWh power; CEO Jamie McAvity named to the Texas Strategic Bitcoin Reserve Advisory Committee (Comptroller, May 28), active from late June |
| Tarbush Mining Site | Lonestar Dream (China Green Agriculture) | 100 shared w/ Pyote | Grid / Tarbush–Leon Creek 138-kV | Primary driver of TNMP's $114.8M upgrade; Woodhouse substation in-service Aug 2026 |
| Blockstream Fort Stockton | Blockstream Services USA | 140 | Grid / CLR | New directory entry — operational since end-2022 under a Ch. 381 agreement; interruptible renewable consumer |
Cormint, Tarbush, and Blockstream remain outside tracker project scope (pure-bitcoin, no reported AI plans); they are archived here for county completeness. The McAvity committee appointment was judged bitcoin-policy color and not logged as a tracker event. The Tarbush Pecos-vs-Reeves geography discrepancy from the June report remains open pending the Reeves County run.
Political overhang
The update frames the month's progress against a hardening state posture: intensified scrutiny of water and power demands, Abbott's rural-ban call, and proposed repeal of the historical sales-tax exemptions that underpin projects like these. Pecos County's bet — trading air-permit headroom and Chapter 381 abatements for multi-billion-dollar off-grid campuses — is now the test case for whether the 2027 session touches the incentive stack.