Data Center Assets and On-Site Generation in Pecos County, Texas
Comprehensive survey, the Waha Hub nexus, off-grid megaprojects, and the grid-tied bitcoin incumbents

Pecos County has become the Permian's proving ground for islanded compute power: Pacifico's GW Ranch (the largest permitted data center power campus in the US) and Poolside's 2 GW Project Horizon both bypass ERCOT entirely on Waha Hub gas, while an older grid-tied generation (Lancium's Clean Campus, Cormint, and the Tarbush mine) pioneered flexible load on the local TNMP system. The county trades multi-billion-dollar Chapter 381 investment against 12,000+ tons/yr of permitted local pollutants, 33M tons/yr of GHG headroom, and severe drought exposure. (Ingest note: this export embedded most numeric values as inline images; figures below are taken from the report's prose and cross-checked against the July 10, 2026 update where the tables were unreadable.)

The Permian energy nexus

Texas is projected to overtake Virginia as the world's largest data center market by 2030, and Pecos County is one of its focal points for massive computing campuses. ERCOT congestion and multi-year interconnection queues pushed county developers toward localized, behind-the-meter, and completely off-grid power — enabled by proximity to the Waha Hub, one of North America's most significant natural gas markets. Self-contained systems combining gas turbines, batteries, and solar accelerate deployment and dodge transmission fees, but concentrate air emissions and water stress in a drought-hit county.

Master directory

Project / developerCapacityGrid postureLandCostWorkloadsTimeline
GW Ranch Energy Center — Pacifico GW LLC7.65 GW gas + 1.8 GW BESS + 750 MW solarSelf-generation, islanded (off-grid private grid)8,000+ build-ready acresMulti-billion (undisclosed)Hyperscale AI computeEarly works mid-2026; Phase 1 (1 GW) H1 2027
Project Horizon — Poolside AI / CoreWeave (per this report)2 GW ultimate; Phase 1 250 MW; 576 MW BTM gasSelf-generation BTM gas (grid backup only)559-acre footprint$5.5B abatement valuation; ~$16B industry-standard for 2 GWCoreWeave (anchor per report) + Poolside AIStart Oct 2025; initial GPUs Dec 2025
Fort Stockton Clean Campus — Lancium, LLC25 MW active / 325 MW plannedERCOT grid (CLR) + Broad Reach Power BESS~200 acres~$800M (Ch. 381 commitment)Bitcoin + high-throughput computeStart late 2021; Phase 1 online Q1 2022
Cormint West Texas — Cormint Data Systems130 MW active; expansion planned by late 2026 (target figure image-embedded in export)ERCOT grid — company-owned 130 MW substation, near Sherbino I Wind814 acres$80M+ equity and debt raisedSelf-mining (bitcoin)Scaling pre-2024; 130 MW mid-2025
Tarbush Mining Site — Lonestar Dream / China Green AgricultureShares 100 MW with Pyote (Ward Co.)ERCOT grid — Tarbush–Leon Creek 138-kV line4143 N US Hwy 285 (see geography flag)$49M stock-purchase acquisitionSelf-mining + hostingActive late 2023

Figures reconstructed from prose and the July 10 update; the June export's table values were embedded as images.