← All Projects

PowerHouse–Provident Grand Prairie Campus

Last updated

Ellis County hyperscale JV
Under construction

The biggest pure-grid play in the Metroplex core: a 1.8 GW, ~810-acre campus between Dallas and Fort Worth from the PowerHouse-Provident joint venture, with its first half-gigawatt already through ERCOT approval.

1.8 GWPlanned power1.8 GW on-site switchyard planned; first 500 MW tranche approved through ERCOT
Developer
PowerHouse Data Centers (AREP) + Provident Data Centers JV
Owner
PowerHouse / Provident joint venture
Tenant
Hyperscale users (TBD): pitched as rapid market entry in the core Metroplex
Power source
ERCOT grid via 1.8 GW on-site switchyard
Cooling
Not disclosed
Compute
TBD
Construction start
Site work from 2025; Building 1's core and shell construction is registered with the state to start April 1, 2026.
Est. completion
First building energized Q1 2027 (originally May 2026); full campus phased. Building 1's core and shell is registered with the state for completion April 1, 2028, a filed date, not the developer's own delivery estimate.
Grid strategy
ERCOT grid
County
Ellis
Nearest city
Grand Prairie (northern Ellis County, DFW)
Announced
2025-02-25