Northampton and Provident North Dallas Corridor Data Center

Last updated

Pre-construction

A 54 MW turnkey data center announced in September 2026 by a new Northampton Capital Partners and Provident Data Centers joint venture, planned for the North Dallas Corridor on a site the partners put at 74 MW and aimed at high density AI inference work, with delivery targeted for late 2027.

54 MWPlanned power
Developer
Northampton Capital Partners and Provident Data Centers joint venture
Power detail
54 MW of critical capacity on what the partners describe as a 74 MW site. The relationship between the two figures was not broken down, and whether the 74 MW is contracted is undisclosed.
Cooling
Described by the partners as using effectively no water
Est. completion
Late 2027 target for delivery
Grid strategy
TBD
Announced
2026-09-03