← All Projects

Crusoe Sweetwater (Nolan County)

Last updated

Pre-construction

A second, separate Sweetwater-area campus: Nolan County commissioners approved a 10-year tax abatement for a $7bn, 200 MW Crusoe Energy Systems data center that will generate its own power, with roughly 2,000 construction workers expected on site. Distinct from IREN's Sweetwater hub and not currently tracked.

200 MWPlanned power
Developer
Crusoe Energy Systems
Owner
Crusoe Energy Systems
Power detail
200 MW. Nolan County commissioners said the facility will supply its own electricity and will draw water through metered wells with reporting obligations; the generation fuel is not named in the coverage retrieved, so the strategy is recorded as off-grid rather than assuming Crusoe's usual behind-the-meter gas model.
Grid strategy
Off-grid
County
Nolan
Nearest city
Sweetwater
Announced
2026-04-13