830-acre east Red Oak campus
Pre-construction

Compass's second Red Oak campus, and the one the town fought: 830 acres on the east side rezoned past midnight on a 4-1 council vote, over its own planning board's recommendation and a room full of neighbours, with the county tax break withdrawn weeks later.

Planned power
Developer
Compass Datacenters
Owner
Compass Datacenters (property under contract)
Power detail
Not disclosed. Coverage describes nearly a dozen data center buildings and several substations at full build, with a closed-loop cooling system designed to reduce water consumption; no megawatt figure has been published.
Grid strategy
ERCOT grid
County
Ellis
Nearest city
Red Oak