← All Projects

Cipher Reveille

Last updated

Reveille
Early works / site prep

The nearest-term site in Cipher's Texas pipeline that is not already energized. Reveille has its ERCOT interconnection approved and substation work underway toward a Q3 2027 target, which puts it past the Batch Zero queue that holds Colchis, Mikeska, McLennan and Apollo. It has no signed tenant: Cipher says it is in discussions for an HPC hosting lease.

70 MWPlanned power
Developer
Cipher Digital
Owner
Cipher Digital
Power detail
70 MW gross with ERCOT interconnection approved, which puts Reveille ahead of Cipher's Batch Zero sites rather than inside the batch. One directory listing describes the site as scalable to 200 MW; Cipher has not published that figure.
Est. completion
Q3 2027 energization target
Grid strategy
ERCOT grid
County
La Salle
Nearest city
Cotulla
Announced
2026-08-04