Project Atlas
Partially operational

A vertically integrated South Texas campus where AZIO develops land, gas supply, onsite generation, electrical distribution, fiber and modular compute together, in order to sidestep the ERCOT interconnection queue. Roughly 6 MW is running today against a stated 500 MW ambition.

11 MWPlanned power
Developer
AZIO AI Holdings
Owner
AZIO AI Holdings
Tenant
Not disclosed
Power detail
Approximately 11 MW of behind-the-meter power secured, of which about 6 MW of compute infrastructure is activated. The company says the site is engineered for up to 500 MW of additional behind-the-meter generation, which is a development target with no disclosed contracts, completed generation or energized load.
Power source
Behind-the-meter natural gas generation, with gas pipeline and metering work disclosed as in progress
Cooling
Not disclosed
Compute
AI and high-density hosting (company-stated objective); no tenant disclosed
Construction start
Not disclosed
Est. completion
Not disclosed
Grid strategy
Behind-the-meter gas
Nearest city
Undisclosed (South Texas)
Announced
2026-08-20