The Load Zone

The weekly Texas AI data center news wire.

THE LOAD ZONE
No. 14 · September 11, 2026

Batch Zero classifications come to light

Five companies published their own conditional ERCOT Batch Zero classifications this week, from IREN's 2,000 MW at Sweetwater to the 1,402 MW Core Scientific split across four different ERCOT categories, while ERCOT published no applicant list of its own and the EIA cut its 2027 regional electricity forecast by 4.7 percent.

The lead

The Batch Zero classifications arrived this week, and every one of them came from the company that received it. IREN said on September 8 that its 2,000 MW Sweetwater Hub was included as base load. Galaxy Digital said the same day that five Texas requests covering about 4.2 GW gross had been classified. CleanSpark disclosed 585 MW conditionally designated Base Load and a separate 300 MW as Studied Load. Core Scientific's 8-K on September 10 covers 1,402 MW across Denton, Pecos and Hunt County. Ionic Digital said ERCOT provisionally classified the remaining 466 MW at its Ward County campus as Base Load.

ERCOT has published no applicant names, locations or capacity figures from its first Batch Zero screening, so each company's own release is the only public account of where its request landed. Galaxy published no location for Caspian, 700 MW, or Selene, 900 MW. CleanSpark gave no breakdown by project.

Base load and studied load are not the same answer. Studied load still has to pass through the Batch Zero system study and capacity allocation. Every classification announced this week is conditional, subject to the audit Abbott ordered on August 3, and ERCOT began issuing verification requests the day before Core Scientific filed.

Locally the answer kept going the other way. White Rose Partners withdrew Project Tomahawk in Prosper on September 8, hours before the council took it up. Pacifico Energy pulled its Bastrop County abatement requests and kept the land. Hays County froze abatements for high-water projects, and Lubbock's council passed a non-binding resolution. The EIA cut its 2027 West South Central sales forecast by 4.7 percent and said the revision reflects the pause.

20Items this week
20Promoted to Intel
829 BBiggest number
The rundown

Galaxy's 4.2 GW came back split. The company said on September 8 that five Texas projects received Batch Zero classifications covering about 4.2 GW gross.

A 477 MW gas plant goes to a city council this month, and nobody has published the load it would serve.

The largest power figure attached to Texas AI load this week is not a deal yet.

Enphase started building in Arlington and has no Texas customer to name.

The wire
Projects & Milestones5
Power & Grid1
Environment & Real Estate1
Finance & Corporate1
Government & Community12

You’re reading The Load Zone, the weekly Texas AI data center news wire from the Texas AI Data Center Intelligence Hub. Items that meet the intelligence bar are promoted into the Intelligence →.