Microsoft holds a right of first refusal on 377 MW at Ward County, granted through Nscale rather than Ionic

Ionic Digital's second quarter presentation, published August 19, 2026, states that Nscale has granted Microsoft a right of first refusal on a further 377 MW at the Ward County campus if that capacity becomes available.