Buildings 1 to 3 in steel framing at Frontier; Building 1 being roofed

Imagery from Apr 14, 2026 shows framing underway on the first three buildings and roofing underway on Building 1, the campus building out in parallel rather than one structure at a time. Epoch, publishing three days later, read the site as consistent with the late-2026 first-building delivery date Vantage has given.