Setback December 16, 2025 Core Scientific Denton (CoreWeave)

Summer storms cost Denton roughly 60 days of concrete pours, pushing the CoreWeave cluster into 2026

Reporting on the Denton conversion put a number on a delay the record had not held: inclement rain and wind stopped contractors pouring concrete for approximately 60 days over the summer, and an alleged transformer fire at the site may also have contributed.