Texas SB 6 becomes law, ERCOT gains curtailment authority over data centers

The regulatory floor for everything in this tracker: large loads must pay their share of transmission costs, maintain on-site backup for 50% of load, and accept curtailment during grid emergencies. Every Texas data center contract now prices curtailment risk. (Late-June date approximate.)