Regulatory March 4, 2025 Last Energy PWR-20 Microreactor Park

Haskell County officials put earliest operation at summer 2029 and place the site at CR 268 and FM 266

KTAB (Abilene) reported Haskell County Judge Kenny Thompson saying the earliest the microreactor park could be running is summer 2029, with Last Energy still working to obtain its federal nuclear permit and state-level permitting also required, a date well beyond the "fabricated, transported and assembled within 24 months" framing in the company's own announcement coverage.