1 tracked AI data center project in Shackelford County, Texas, 1.4 GW of disclosed planned capacity across 1 of them. Status: 1 under construction.

1Tracked projects
1.4 GWDisclosed capacity
4Operators
1.53MW per sq mi914.3 sq mi of land

Status

  • 1 Under construction

Power strategy

  • 1 Off-grid

Projects

  • Vantage “Frontier” Campus (Stargate Shackelford) Under construction · 1.4 GW · Albany / Moran (near Abilene)

    Vantage's largest-ever campus: ten buildings and 1.4 GW on 1,200 acres, developed with Oracle as part of Stargate's Texas expansion, with its own off-grid gas microgrid sidestepping the ERCOT interconnection queue.