Midland County

4 tracked AI data center projects in Midland County, Texas, 155 MW of disclosed planned capacity across 2 of them. Status: 3 partially operational, 1 early works / site prep.

4Tracked projects
155 MWDisclosed capacity
6Operators
0.17MW per sq mi900.4 sq mi of land

Status

  • 3 Partially operational
  • 1 Early works / site prep

Power strategy

  • 3 ERCOT grid
  • 1 Off-grid

Projects

  • FO Permian Partners Data Center Early works / site prep · 150 MW · Midland

    Midland County's flagship off-grid play: 150 MW of gas-and-battery-powered critical IT on 320 of 3,200 acres, engineered by FO Permian and IPP HiVolt Energy to skip the ERCOT queue entirely and deliver Phase 1 by late 2026.

  • BBT Midland 1 Partially operational · 5 MW · Midland

    Midland County's incumbent edge asset: a 5 MW-master-planned, MCFI-built modular colo that Big Bend Telephone has run since January 2022, feeding low-latency connectivity to Permian oil and gas operators from a retrofitted 5,200 sq ft building.

  • 1102 McKinzie LLC Data Center Partially operational · — · Midland

    A registry-visible black box: a grid-connected Midland County data center known almost entirely through its Texas Data Center Program exemption, which statutorily commits at least $200M of qualifying investment while every physical parameter stays proprietary.

  • 1242 McKinzie LLC Data Center Partially operational · — · Midland

    The second half of Midland's proprietary McKinzie campus: 1242 McKinzie LLC holds the real estate, 1102 McKinzie LLC operates, and a June 2024 tax-program registration marks a further $200M-minimum capital deployment with zero disclosed specs.