El Paso County

Last updated

2 tracked AI data center projects in El Paso County, Texas, 4.0 GW of disclosed planned capacity across 2 of them. Status: 1 under construction, 1 pre-construction.

2Tracked projects
4.0 GWDisclosed capacity
5Operators
3.95MW per sq mi1,013.5 sq mi of land

Status

  • 1 Under construction
  • 1 Pre-construction

Power strategy

  • 1 Hybrid (grid + on-site)
  • 1 TBD

Projects

  • Fort Bliss Data Center Pre-construction · 3.0 GW · El Paso (far east: Loop 375 & Montana Ave.)

    The Army wants a 3-gigawatt AI data center on Fort Bliss land in far east El Paso (more electricity than all 460,000 of El Paso Electric's customers combined) and has conditionally picked the Carlyle Group to build and operate it. Nothing is signed: environmental review is pending, the power source is undecided between combined-cycle gas and an off-grid independent producer, and the Army's "water neutral" pledge over the Hueco Bolson aquifer has no published mechanism.

  • Meta El Paso Data Center Under construction · 1.0 GW · Northeast El Paso

    Meta's third Texas site grew sixfold in months, from a $1.5B plan to a $10B+, 1 GW campus that will dominate El Paso's grid planning, with a dedicated gas-generator plant under PUC review. On Jul 28, 2026, Meta and BlackRock formalized a financing venture (BlackRock funds own 80%, Meta retains 20% and remains the initial sole occupant), shifting most ownership and financing risk to outside infrastructure capital.