3 tracked AI data center projects in Angelina County, Texas, 2.2 GW of disclosed planned capacity across 2 of them. Status: 1 early works / site prep, 2 pre-construction.

3Tracked projects
2.2 GWDisclosed capacity
4Operators
2.7MW per sq mi797.9 sq mi of land

Status

  • 1 Early works / site prep
  • 2 Pre-construction

Power strategy

  • 1 ERCOT grid
  • 1 Off-grid
  • 1 Hybrid (grid + on-site)

Projects

  • Project Lufkin Pre-construction · 2.1 GW · Lufkin

    AmpZ Champion Data Center Holdings (parent: Amp Energy) is redeveloping the 1,041-acre former Southland Paper Mill site on SH-103 East into a phased hybrid AI campus (from a 55 MW grid connection today to an ultimate 2.1 GW by 2029) while negotiating Chapter 381 protections against organized local opposition and running a closed-loop water system that cuts site water use from the legacy mill's 20 million gallons/day to about 500 gallons/day.

  • 555 Sellers Street Data Center Pre-construction · 55 MW · Lufkin (north of city)

    Phoenix-based 1606 Corp is acquiring a 132-acre parcel north of Lufkin (a decommissioned 55 MW woody-biomass power plant (former Aspen Power, to be operated by Sim Agro Inc.) plus an existing 50,000 sq ft warehouse) to run AI/HPC workloads on captive, behind-the-meter power, bypassing ERCOT interconnection delays.

  • HyperDataGrid Hudson Data Center Early works / site prep · — · Hudson

    A Houston-based developer quietly began building a small AI data center on a former East Texas chip mill site in Hudson, months ahead of the far more publicized AmpZ proposal a few miles away, and it has already locked down the power and water agreements AmpZ still lacks.